MA Ltd Contribution to the A2S project:
MA Ltd was involved in the preparation and delivery of all UK fieldwork relating to the A2S project. This ranged from Geophysical survey to deep water diving and underwater excavation with a 5 man HSE dive team. As well as the fieldwork MA Ltd also provided specialist services for the processing of geophysical data.
2009
Contributions to Activity 1 (Data Collection) – Processing of Geophysical Data
2010
Dive contractor for Activity 3 (Fieldwork), included preparation, boat hire and 5 man HSE dive team
7th – 11th June
21st – 25th June
5th – 9th July
2nd – 6th August
22nd – 27th August
5 days geophysical Survey
Further Processing of geophysical data
2011
Dive contractor for Activity 3 (Fieldwork), included preparation, boat hire and 4 man HSE dive team
23rd May – 27th May
27th June – 1st July
21st July – 27th July
8th August – 10th August
5th September – 9th September
22nd September – 23rd September